As noted by the mayor of the city Anatoly Lokot, 220 yards will be repaired at the expense of regional and municipal programs aimed at the creation of a comfortable living environment.

the Programme of improving courtyards of this year, formed according to the mandates of the deputies of Council of deputies of Novosibirsk and of the Legislative Assembly. The program mandates for these purposes will be directed 420 million roubles, – said Anatoly Elbow during the exit meeting devoted to the issues of improvement of courtyard territories in Zaeltsovsky area.

On the territory adjacent to house No. 163 main street, is already under construction – removed old asphalt, Packed gravel, began paving a large area. Also here is extended car Parking, the curbs are installed. According to Chairman TSZH “Krasnyy Prospekt, 163” Vadim Vihrova, at a General meeting of residents was also reviewed and approved the redevelopment plan of the yard, including landscaping, drainage, construction of playgrounds, Parking spaces, sidewalks, walkways and driveway. The total cost of works will amount to 5.3 million rubles. According to the contractor – the company “Dorstroytsentr”, to complete the work is scheduled until mid-may.

– we have questions. For example, on the yard after the rain always formed a puddle. Stormwater in this location is not provided, but I want to see the rain did not become a disaster for residents, – said Vadim Vikhrov.

the mayor asked the head of the Department of energy, housing and communal services Dmitry Peryazev and representatives of contractor organizations when possible to accommodate the wish of the residents.

One of the main problems facing the residents of MCD in coordination of plans for the landscaping of yards, to be whether the Parking lot or the Playground.

– as time passes, those who now wants a place in the yard under my car, asks: “where’s the Playground?”. Children should be safe territory for games and sports, – expressed his point of view, the mayor.

Anatoly Lokot has noticed that thanks to good weather (in Novosibirsk for a week the temperature does not fall below 17-20 degrees), the repairs of the road network and intra-territories began a month earlier than usual. So, out of 220 planned repair yards in the 33 already underway, five – renovated, 96-yards – carried out preparatory work on the remaining contests for the selection of contractors.

We for the first time in many years, has deployed a complete scope of work in April. It is necessary to use good weather. This will allow soon to finish landscaping work, to improve their efficiency and quality. Until October all work must be completed, but given the early start, I think 1 CE��of October – the beginning of a new academic year, our yards should be transformed, – said the mayor Anatoly Elbow.

the mayor’s office noted that Russia participates in the Federal priority program “Formation of a comfortable urban environment”. It additionally repaired 46 intra-territories. The total amount of funds it will amount to 170 million rubles. These facilities are comprehensively equipped. Includes not only the paving of house adjoining territories, but also the equipment of playgrounds and sports grounds, installation of lighting, urns, benches, planters and other landscaping elements and planting. This will take into account the interests of different social and age groups of the population.

However, to participate in the project according to the Federal legislation required co-financing not only from the city budget and residents. As explained in city Department of power and housing and communal services, in 2020 the owners of premises in apartment houses should provide co-financing additional list of improvement works in an amount not less than 20 percent of its value.

residents believe that the harmonization of plans of improvement of courtyard territories must always be taken into account. No plan is approved in the relevant departments without the wishes of the citizens. Comments and suggestions must take into account a contractor, – noted Anatoly Elbow.

Given the difficult epidemiological situation in the region due to coronavirus, this year held an online presentation of projects of improvement of house adjoining territories MKD and public spaces. Residents can voice their suggestions in an online format.

Also, the mayor together with specialists to monitor the progress of work on the local area streets between Spring and Galilee. Here are settling entrance areas, sidewalks, walkways, car Park, will be renovated travel, organized drainage channel. Landscaping will spend almost 8.5 million rubles. Contractor. SK “Sibstroy” plans to complete the work in early June.